Creation of housing conditions for IDPs in the town of Mariupol/137, Nikopolsky av. (apartments for IDPs temporary residence/KfW) 16-14-00-001
State: Warranty period
Project measures: | |
|---|---|
| Settlement | town of Mariupol |
| The main typology | apartments-for-idp |
| Address of the object | Nikopolsky Ave., 137, Mariupol, Donetsk region |
| Main works and activities | Creation of housing conditions for IDPs in the town of Mariupol/137, Nikopolsky av. (apartments for IDPs temporary residence/KfW) |
| Implementation period | 05.10.2020 - 30.04.2021 |
| Percentage of completion of work | 100% - 02.11.2021 |
| Cost of subproject | 5287284,42 грн. (UAH) |
| Area m2 | 450,0 |
| Contractor type | LLC SPE "Contact Sich-Aqua" |
| Number of Beneficiaries | 24 |
Works stages
Project is completed