Improvement conditions of primary health care in Shtormivska village outpatient clinic, village of Shtormove, Novoaidar district, Luhansk region/KfW - 19-44-19
State: Selection of contractors
Project measures: | |
---|---|
Settlement | Shtormove |
The main typology | Primary health care |
Address of the object | Luhansk region, Shchastynskyi district, Shtormove village, Akademika Amosova street, 3 |
Main works and activities | Replacement of windows and doors - 25 m2;
Facade insulation (150 mm) - 310 m2;
Overhaul of the roof with insulation - 280 m2;
Overhaul of internal premises - 216.55 m2; |
Implementation period | 2021-2022 |
Percentage of completion of work | 0% |
Cost of subproject | 0,00 |
Area m2 | 216.55 |
Number of Beneficiaries | 1724 |
Works stages



Receipt of documentation
Works in progress
Warranty period
Project is completed