State: Project is completed
Completed

School №1 Zolochiv village

Project measures:
Settlement Zolochiv village
The main typology Preschool and basic education
Address of the object 25 Centralna street, Zolochiv village, Kharkiv region
Main works and activities

Reconstruction of the roof with insulation, insulation of the base, installation of the oven

Implementation period 25.04.2016 - 01.09.2017
Percentage of completion of work 100%
Area m2 3 720,00
Contractor type ‘Spetsvohneizoliatsiia’ LLC, ‘Firma Mobikom’ LLC
Number of Beneficiaries 1182
Works stages
Selected for financing
Documentation in the process of development
Selection of contractors
Receipt of documentation
Works in progress
Warranty period
Project is completed
Additional commentary

The building is built without taking into account modern energy saving norms, windows and an entrance door group in an emergency due to long-term operation. As a result, the temperature regime in the premises of the secondary school is not observed. Every year, by the community, only cosmetic repairs of the premises are carried out, and the community does not have sufficient funds to solve the priority problem on its own. The community has no way to solve the problem on its own. The project is very important for the community