SUPPORT TO SOCIAL INFRASTRUCTURE DEVELOPMENT, SP № 14-23-00-003
State: Project is completed
Completed
As a result of repairs in the institution, clients and staff received more favorable living and working conditions, as well as improved quality of provision and reception of social services at the institution.
Project measures: | |
---|---|
Main works and activities | Replacement of the roof with insulation of the ceiling, insulation of the facade, replacement of windows for energy saving, replacement of doors, interior finishing works, replacement of all internal and external engineering networks, arrangement of accom |
Implementation period | 26.04.2016 – 30.01.2019 |
Percentage of completion of work | 100% |
Area m2 | 688,00 |
Contractor type | "Ukrliftkomplekt" LLC |
Number of Beneficiaries | 50 |