State: Project is completed
Completed

In Lviv there was no social housing where IDP`s could live. Thanks to the implementation of the subproject, 80 bed places were created for the accommodation of internally displaced persons and the starting conditions for their establishment and adaptation.There is also 10 bed places for orphans who reached the age stage between 18-35 years old.

Project measures:
Settlement Lviv
Address of the object 2 Ugorska street, Lviv city
Main works and activities

Roofing. Windows replacing. Internal door installations. External door installations. General construction works (interior decoration of premises). Installation and customizing of the heat supply station. Installation of internal engineering networks.

Implementation period 05.01.2016-28.02.2019
Percentage of completion of work 100%
Area m2 2 205
Contractor type “Plast” LLC
Number of Beneficiaries 1440
Works stages
Selected for financing
Documentation in the process of development
Selection of contractors
Receipt of documentation
Works in progress
Warranty period
Project is completed