Improvement conditions of primary health care in Verhniotersianska OCGP of Guliapilsky PHCC, village of Verhnia Tersa, Guliapilsky district, Zaporizhzhia region/KfW - 20-23-38
State: Works in progress
Project measures: | |
---|---|
Settlement | Verhnia Tersa |
The main typology | Primary health care |
Address of the object | with. Verhnia Tersa, street Central, 78b, Zaporozhye region. |
Main works and activities | Facade insulation (150 mm) - 271 m2;
Replacement of doors - 8 m2;
Overhaul of the roof with insulation - 238 m2;
Overhaul of internal premises - 188.10 m2;
Landscaping - 127 m2; |
Implementation period | 08.06.2021 - 25.02.2022 |
Percentage of completion of work | 42% - 19.12.2021 |
Cost of subproject | 5 599 946,4 грн. (UAH) |
Area m2 | 188.10 |
Contractor type | LLC "Alexander" |
Number of Beneficiaries | 1824 |
Works stages
Warranty period
Project is completed