USIF-VI

‘Promotion of Social Infrastructure Development. USIF.VI’ Project
Implementation period: 2018 - 2023
Donor: German Government through KfW)
Budget: EUR 9 mln.
Territory of implementation: Dnipropetrovsk, Zaporizhzhia and Kharkiv regions, districts of Donetsk and Luhansk regions under control of Ukraine.
Objectives: provision of internally displaced persons (IDPs) with housing, improvement of social objects (schools and pre-school institutions) infrastructure in the communities, hosting IDPs.

26 objects (subprojects), including 13 residential buildings (basic subprojects), 4 school and 8 kindergarten facilities (secondary subprojects), located in

  • Dnipropetrovsk region: Kryvy Rih, Pershotravensk;
  • Donetsk region: Mariupol;
  • Zaporizhzhia region: Melitopol, Lantseve (Komysh-Zoryanska amalgamated territorial community), Gulyaypole;
  • Luhansk region: Severodonetsk, Novoaydar, Kreminna;
  • Kharkiv region: Izyum, Chuguiv

were selected for implementation.

Implementation status as of June 2022:

Initially planned construction works have been completed within 20 out of 26 subprojects (SPs).

Additional works have been fully executed within 5 out 7 SPs, where they were planned.

A number of capacity building programs and measures for partner communities have been conducted within the framework of the Project. "Promotion of IDPs and Local Residents Employment", ‘Legal support to local self-government authorities and IDPs’ and ‘Inclusion in communities’ programs have been successfully implemented in particular. Most of the planned activities within ‘Development of social services in communities’ program have been accomplished.

Numerous measures have been taken to ensure efficient work in the areas of environmental and social management and management of asbestos-containing materials.

Interested persons can get acquainted with Environmental and Social Management Framework (ESMF) related to this Project.

As the military aggression of the russian federation did not allow to continue the implementation of the Project as it was planned, USIF Executive Committee, after careful study of the situation and consultation with a donor representative (KfW), recognized the:

- impossibility of further implementation of 2 SPs for creation of housing for IDPs in Izyum, Kharkiv region and Lantseve village, Zaporizhzhia region;

- need to cease execution of additional works in the framework of 2 SPs related to renovation of educational institutions in Blagovishchenka village, Zaporizhzhia region and Mariupol, Donetsk region and suspend the initially planned construction works at the objects of 2 SPs in Chuguiv, Kharkiv region as well as 2 SPs in Gulyaypole, Zaporizhzhia region.

Construction works on IDP housing facility in Chuguiv, Kharkiv region are already resumed.

In order to continue construction works on another facility in Chuguiv - gymnasium №5, preparations for tender selection of a contractor are underway.

The troublesome security situation still does not allow to resume implementation of 2 other SPs (IDP housing and kindergarten facilities) in Gulyaypole, Zaporizhzhia region.