Creation of housing conditions for IDPs in the town of Mariupol/27, Ryzka str. (apartments for IDPs temporary residence/KfW) - 16-14-00-002
State: Works in progress
Project measures: | |
---|---|
Settlement | town of Mariupol |
The main typology | apartments-for-idp |
Address of the object | 27, Ryzʹka street town of Mariupol |
Main works and activities | The project provides for the arrangement of 4 one-room apartments.
Replacement of windows - 12 / 26.88 pcs / m2
Replacement of doors - 19 / 26.67 blocks / m2
Repair of walls - 665.4 m2
Floor repair - 165.7 m2
Repair of the ceiling - 165.7 m2
Installation of gas boilers - 4.0 sets
Installation of radiators - 16.0 sets.
Laying of sewerage pipelines - 73.3 m.p.
Laying of water supply pipelines - 126.0 m.p.
Laying of electric networks - 1060,0 m.p.
Facade insulation - 245.0 m2
Arrangement of the stage - 61.0 m2
Roof repair - 204 m2
|
Implementation period | 16.11.2020 - 30.09.2021 |
Percentage of completion of work | 100% - 19..12.2021 |
Area m2 | 169,1 м2 |
Contractor type | LLC "PSP Kronos" |
Number of Beneficiaries | 12 |
Works stages
Warranty period
Project is completed