Support to Social Infrastructure Development

Support to Social Infrastructure Development
Статус: Проект завершено
Completed

Project measures:
Settlement Verkhivtsevo city
Address of the object Verkhivtsevsky dstr., Dnipropetrovskyi region, Zaliznychna street, 1a
Main works and activities Repair of the roof, replacement of windows for energy saving, insulation of facades
Implementation period 14.05.2016 – 22.05.2019
Percentage of completion of work 100
Cost of subproject 8000000
Area m2 950
Cost per m2, UAH 8421
The share of KfW / Partner funding 100/0
Contractor type AstaMonolit LLC
Number of Beneficiaries 480
Works stages
Selected for financing
Documentation in the process of development
Selection of contractors
Receipt of documentation
Works in progress
Warranty period
Project is completed
Additional commentary

As a result of the repairs in the orphanage, wards and staff will receive more favorable living and working conditions. This will lower the temperature regime in the two-story building and increase the quality of providing and receiving social services in the institution. During the implementation of the micro-project in the community, positive developments are expected, such as the creation of additional 20 beds for IDP.