Support to Social Infrastructure Development

Support to Social Infrastructure Development
Статус: Проект завершено
Completed

Project measures:
Settlement Vilnogirsk city
Address of the object Centralna str., 45a
Main works and activities Replacement of windows for energy-saving, replacement of external doors on metal insulated
Implementation period 06.04.2016 – 20.07.2017
Percentage of completion of work 100
Cost of subproject 3170000
Area m2 1800
Cost per m2, UAH 1761
The share of KfW / Partner funding 100/0
Contractor type Ekipag PE
Number of Beneficiaries 480
Works stages
Selected for financing
Documentation in the process of development
Selection of contractors
Receipt of documentation
Works in progress
Warranty period
Project is completed
Additional commentary

Children and educators have received appropriate and comfortable learning and working conditions. This increased the quality of provision and reception of services in secondary schools, reduced morbidity. Students get full development of their abilities, skills and abilities.