SUPPORT TO SOCIAL INFRASTRUCTURE DEVELOPMENT

SUPPORT TO SOCIAL INFRASTRUCTURE DEVELOPMENT
Статус: Проект завершено
Completed

Project measures:
Settlement Melitopol city
Address of the object Yaroslava Mudrogo str., 10A
Main works and activities Insulation of the facade, replacement of the doors, placement of the scaffolding around the building, improvement, ramp mounting
Implementation period 13.04.2016 – 15.06.2017
Percentage of completion of work 100
Cost of subproject 2600000
Area m2 3235,5
Cost per m2, UAH 803
The share of KfW / Partner funding 100/0
Contractor type "Avega" LLC
Number of Beneficiaries 445
Works stages
Selected for financing
Documentation in the process of development
Selection of contractors
Receipt of documentation
Works in progress
Warranty period
Project is completed